With this PPP project, the city and project company aim to fulfill the statutory obligations of the city, which has official responsibility for the schools, to ensure sufficient and appropriate school space and to run the schools in line with regulations for the duration of the contractual period of 25 years. |
Object data |
- | first pilot project of the Federal Government?s PPP Task Force |
- | 9 schools with sports halls and additional facilities at 8 locations |
- | approx. 67,000 m² gross floor space |
- | approx. 63,000 m² outside space |
- | project start in January 2007 |
- | start of construction in August 2007 |
- | start of operation: 4 school sites August 2008, 4 sites August 2009 |
- | period of operation: 25 years |
Range of services |
Technical facility management |
- | operation, maintenance of technical facilities, maintenance or structural maintenance of the building as a whole, emergency and breakdown service with 24-hour helpline, energy management and media supply. |
Infrastructural facility management |
- | area and removal management, cleaning and maintenance of outside areas, supply and disposal services, winter service and building, façades and glass cleaning. |
Commercial facility management |
- | reporting or documentation, FM controlling and contract management. |
| |